Written Answers - Schools Building Projects.Tuesday, 26 February 2008 |
Dáil Eireann Debate
Page of 360
|
310.
Deputy Brian Hayes
asked the
Minister for Education and Science for
the names of primary schools in each county where school building projects were progressed to completion during 2007 under the permanent accommodation scheme.
[7422/08]
Minister for Education and Science (Deputy Mary Hanafin):
In the period 2003 to 2007, 335 primary and post primary schools accepted an allocation of funding under the Permanent Accommodation Scheme at a cost in excess of €103m. This Scheme allows schools to proceed with small scale permanent building projects with minimum interaction with my Department. Of the 335 approved projects, 166 were completed by the end of 2007, 47 are on site and the remainder are in advanced stages of architectural planning. I will arrange to forward a list of the projects to the Deputy.
| Last Updated: 08/10/2010 08:29:43 |
Page of 360
|